Fibermark
Warren Glen Facility
Bloomsbury, New Jersey
Project:
Plant Upgrades
Contract Value:
$650,000+
Maximum
Manpower Load:
14
Duration of
Max. Load:
1 month
Challenges
1. Antiquated Facility
2. Aggressive Shutdown Schedules
3. No Documentation
Procter
& Gamble
Mehoopany, Pennsylvania
Project:
Parson's Infrastructure & Technology
Project:
Baby Care Project
Contract Value:
$1,956,000
Maximum
Manpower Load:
40
Duration of
Max. Load:
2 months
Challenges
1. Very Large Work Area
2. Intensive Decision Making Process
3. Extremely Accelerated Schedule
4. "Engineer - Procure - Construct"
5. Concept Requiring Many Field Changes